Short answer: a BOM lists the components and quantities in a product. A routing lists the operations that build it, in order, with a work center, setup time and run time for each. The BOM drives material planning and material cost. The routing drives scheduling, capacity and labor cost. Three things connect them, and that is where they go wrong: the operation each component is consumed at, the option rules that switch both parts and operations on, and the routing times your quote was priced with.
The pages that rank for this explain the split well.Fabrico puts it as materials structure versus process structure,Customiser has a good job-shop table of what a routing line holds, andSAP Learningshows how product costing reads quantities from the BOM and times from the routing. If you only need the definitions, start there.
What they leave out is that a BOM and a routing are two records maintained by two people, often in two screens, with their own revisions. The definitions are never what goes wrong. The links between the two records are.
What each record holds, and who edits it
| BOM | Routing | |
|---|---|---|
| One line is | A component, quantity per parent, unit | An operation: number, work center, setup and run time |
| Changed by | Engineering change, substitution, new option | New machine, time study, rate change, outsourcing a step |
| Usually edited by | Design or manufacturing engineering | Manufacturing engineering, estimating, planning |
| An error shows up as | Shortage, wrong part picked, material variance | Late orders, overloaded work center, labor variance |
| Often wrong without anyone noticing | Which operation each part is used at | Whether the times still match the floor |
The bottom row sits between the two records, and each owner tends to assume the other one maintains it.
Link 1: which operation consumes which part
Every ERP with routings has some way to say "this component is used at this operation." It decides where the part is staged, and in systems that backflush, when it is posted as consumed.
- SAP assigns BOM items to operations through component allocation in the routing (CA02). Components with no assignmentdefault to the first operation, and orders created before you fix it need their master data read again. Practitioners on SAP Community note that the backflush flag can be set right there, per component and operation.
- Odoo has aConsumed in Operationcolumn on BoM component lines. It is hidden until you switch it on in the column settings, so it is easy to leave empty.
- NetSuite links amanufacturing routing to a bill of materials, and its Component per Operation subtab has a line for each component and revision combination. A new BOM revision brings new lines that someone still has to assign to an operation.
The failure is quiet. The BOM is right, the routing is right, and the part is still issued at the wrong station or posted as consumed before anyone touches it.
Link 2: options that add a part usually add a step
For configured products, an option rarely changes only the parts list. A motorized operator adds a motor kit and also adds the time to fit, wire and test it. ERPs let you put a condition on both. Odoo hasApply on Variantsfor component lines and, separately, for operations. SAP variant configuration uses asuper task listin which each optional operation carries its own selection condition, alongside the ones on the super BOM.
So one business rule, "motorized means motor kit plus motor fitting," is written twice in two places, often by two people. When they disagree, you get one of two errors. If the part's condition is right and the operation has none, every manual unit carries time it doesn't need, and the work center looks overloaded. If the operation is missing, motorized units are under-costed and under-scheduled.
Link 3: the times the quote was priced with
Quotes for made-to-order products price labor from somewhere: a labor table in CPQ, an estimator's spreadsheet, or a routing copied at order entry. That source drifts from the routing the plant runs. Two causes are common. Run times change after a time study and nobody updates the quote tables. Setup gets spread over a standard lot size when the actual order is smaller.SourceXmakes the point well for job shops: compare estimate to actual by operation, keep setup and run separate, and keep the routing that priced the job frozen. The prerequisite is that the quote states which operations and which times it used.
A worked example: one option, three drifts
This example is invented; it is not a customer record. A window maker builds the Cascade 440. Its routing has five standard operations plus op 45, "fit motor, wire, test," for the motorized option. All work centers cost $90 an hour. CPQ prices the motor option's labor from a table entered when op 45 took 9 minutes. After a time study it takes 14. CPQ also spreads the 45 minutes of setup (ops 10 to 30) over a lot of 50 units. A customer orders 14 motorized units, built as one lot.
| Item | Quote (CPQ) | BOM | Routing | Effect |
|---|---|---|---|---|
| Motor fitting time | 9 min, $13.50 | — | op 45: 14 min, $21.00 | $7.50 a unit missing from the quote's cost, $105 on 14 units |
| Setup per unit | 45 min ÷ 50 = $1.35 | — | 45 min per lot = $67.50 | $67.50 − 14 × $1.35 = $48.60 missing |
| Motor kit consumed at | — | Line added for motorized, no operation set | Defaults to op 10, cut | Kit staged at the saw and backflushed at the first confirmation |
| Condition on op 45 | — | Kit: motorized only | None, so op 45 applies to every unit | Every manual window loads 14 extra minutes on assy-2 |
The quote's labor cost is $153.60 short on this order ($105.00 + $48.60) before anything goes wrong on the floor. The price may still be fine. The margin report is not, and nobody will see why, because the quote never recorded which times it used. The kit drift costs no money on a good day. When a frame is scrapped at welding, the system has already posted its motor kit as consumed while the kit is still on the shelf, so inventory is off by one kit for every scrapped frame. The op 45 condition makes the assembly cell look busier than it is, and planners start moving work that didn't need to move.
Below, the same product is kept as one graph, using the draft format described inA bill of materials in JSON. Components point at the operation that uses them. The motorized condition is written the same way on the part and on the step, and the quote's labor is read from the operations instead of a separate table:
{
"product": "bom.win.cw-440",
"rate_usd_per_hr": { "assy-2": 90, "saw-1": 90, "weld-1": 90, "glaze-1": 90 },
"operations": [
{ "id": "op10", "name": "cut profiles", "at": "saw-1", "setup_min": 20, "run_min": 6 },
{ "id": "op20", "name": "weld, clean corners", "at": "weld-1", "setup_min": 15, "run_min": 9 },
{ "id": "op30", "name": "glaze", "at": "glaze-1", "setup_min": 10, "run_min": 12 },
{ "id": "op40", "name": "hardware", "at": "assy-2", "run_min": 8 },
{ "id": "op45", "name": "fit motor, wire, test", "at": "assy-2", "run_min": 14,
"when": "operator == 'motorized'" },
{ "id": "op50", "name": "inspect, pack", "at": "assy-2", "run_min": 5 }
],
"components": [
{ "id": "c.frame-profile", "qty": 6.2, "unit": "m", "used_at": "op10" },
{ "id": "c.igu-low-e", "qty": 1, "unit": "ea", "used_at": "op30" },
{ "id": "c.hinge-set", "qty": 1, "unit": "set", "used_at": "op40" },
{ "id": "c.motor-kit-m2", "qty": 1, "unit": "ea", "used_at": "op45",
"when": "operator == 'motorized'" }
],
"quote_labor": { "from": "operations", "setup_spread_over": "order_qty" }
}With this shape, the three drifts are checks a script can run. Every component needs aused_at that exists. A when on a component must match one on its operation. The quote reads labor from the operations, so it carries no separate times that could go stale.
Do you need a routing at all?
Not always. If a product is picked and assembled in one step at one bench, a BOM with a labor line is honest and simpler. A routing earns its keep when any of these is true:
- Work passes through two or more work centers that can become bottlenecks.
- You quote labor or machine time as part of the price, not as a flat margin.
- You backflush components, or stage them at the station that uses them.
- An option or variant adds or removes a step, not only a part.
Checks to run on your own BOMs and routings
- List every component with no operation assignment. In SAP, compare against the first operation, which is where the unassigned ones went.
- For each option with a condition on a BOM line, look for the matching condition on an operation. Then do the reverse.
- Pick your five highest-volume configured products and check that the labor on the quote can be traced to routing operations and times.
- Compare the lot size the quote spreads setup over with the median order quantity over the last year.
- After each BOM revision, check that the new revision's components are assigned to operations (NetSuite shows a line for each revision).
- For alternative routings, confirm that every assigned component is assigned in each alternative, not only in the default.
- Find the date of the last time study on each work center, and the date the quote labor tables were last changed. The gap between them tells you how stale the quote times are.
Where SingleBOM fits, and where it doesn't
SingleBOM keeps parts, operations, option conditions and the quote's cost basis in one JSON graph. The consumed-at link and the shared condition are part of the data, not a setting in a second screen. That addresses the three links above, and it gives the quote a record of which operations and times it used.
It does not schedule. It is not an MES or a capacity planner, it does not collect labor tickets, and the format is still a draft with no hosted service. If one ERP configurator already generates both your order BOM and your order routing from the same rules, and your quotes read times from that routing, you already have most of this. Use the checks above to confirm it. Process manufacturers on recipes have a different structure, and this article does not cover it.